Illustrative study — supplied sample content. The scenario, simulation visuals and numerical results below are examples supplied for this website. They are not independently verified IMBEST project results, client endorsements or performance guarantees. Method, feasibility and delivery scope must be confirmed for each enquiry.
CFD Flow & Mixing Analysis of a Chlorine Contact Tank
Eliminating short-circuiting through baffle redesign to meet CT disinfection requirements without expanding the tank.
01 — ChallengeCT requirement not met due to short-circuiting
A wastewater treatment plant’s chlorine contact tank was not meeting CT (concentration × time) disinfection requirements. Short-circuiting through the tank was suspected but unconfirmed.
02 — Approach3D CFD with residence time distribution analysis
A full 3D model with baffle geometry, free-surface modeling, and residence time distribution (RTD) tracer analysis was run across low, average, and peak flow conditions to quantify hydraulic efficiency.
03 — Simulation ResultFlow pattern after adding baffle walls
Flow pattern after adding baffle wallsFig. 1 of 1
04 — Quantified ResultsBefore / After
| Parameter | Baseline | Result | |
|---|---|---|---|
| Hydraulic efficiency (T10/T̄) | 0.38 | → | 0.74 |
| CT achievement at peak flow | 68% of requirement | → | 104% of requirement |
| Identified dead zones | present | → | eliminated |
05 — Business Impact
Achieved disinfection compliance without a tank expansion, saving an estimated 6 months on the construction schedule.